George Mason University
George Mason University Mason
George Mason University

Project Timeline

CORE CAMPUS PROJECT TIMELINE
Horizon Hall (New Academic Building) and Utility Infrastructure Upgrade

 

FALL 2020

 Horizon Hall

  • Final site work completed
  • Elevator installation completed
  • Finishes completed
  • Install audio/visual equipment
  • Install furniture, fixtures, and equipment

Utility Infrastructure Upgrade

  • Final landscape restoration throughout Phases 3, 4, 5 and 6
  • Salvage of Phase 7 area site features
  • Demolition and removal of existing sidewalk, steps, pavers in Phase 7 area
  • Complete trenching, utility installation and backfill of Phase 7
  • Install storm water structure in south area of student housing laydown area

START PHASE 8

  • Wilkins Plaza, North side
  • Deliver and install site fencing and erosion and sediment controls for Phase 8 area over winter break

Planned Outages

  • Thanksgiving Break (Nov. 25–29): Chilled water outage, de Laski Performing Arts Building and Center for the Arts

SPRING 2021

Horizon Hall

  • Horizon Hall projected opening for start of spring 2021 classes
  • Robinson B is vacated and decommissioned; hazardous materials removed and demolished
  • Harris Theatre closes for renovations

Utility Infrastructure Upgrade

  • Complete Wilkins Plaza upgrades: new sidewalk, pavers with concrete base and statue base in Phase 7 area
  • Complete sod and vegetation installation in Phase 7 area
  • Demolition and removal of existing sidewalk, steps, pavers in Phase 8 area
  • Complete trenching, utility installation, and backfill of Phase 8 area
  • Install new water feature fountain as part of Phase 8 area
  • Complete Wilkins Plaza upgrades: new sidewalk, pavers with concrete base and statue base in Phase 8 area

Planned Outages

None

SUMMER 2021

Horizon Hall

  • Site work begins in area of demolished Robinson B building
  • Harris Theatre addition and renovations continue

Utility Infrastructure Upgrade

  • Complete sod and vegetation installation in Phase 8 area
  • Re-install George Mason statue

Planned Outages

  • July 2–5: Chilled water outage, Student Union Building I (SUB I)

FALL 2021

Horizon Hall

  • Site work is complete by end of fall 2021
  • Harris Theatre renovations are complete by end of fall 2021

Utility Infrastructure Upgrade

  • Complete punch list items for utilities distribution infrastructure project

Planned Outages

None