Core Campus Project: Two-Week Planner, October 21 to November 1

Robinson Hall Replacement

Week of October 21:

  • Continue steel erection moving south and then up to roof and repeat starting at north end of building.
  • Offsite work is progressing on coordination and inspections of prefabricated electrical rooms that are being fabricated offsite in a warehouse facility in southern Virginia.   
  • Continue installation of elevated underfloor mechanical and electrical and telecom utilities.
  • Continue installation of brick on building elevation mock up.
  • Continue installation of underground utilities on north and south ends of new building.
  • Start layout of partitions on floor 3.
  • Start spray on fireproofing on floor 1.

Week of October 28:

  • Continue steel erection moving south and then up to clerestory starting at north end of building.
  • Offsite work is progressing on coordination and inspections of pre-fabricated electrical rooms that are being fabricated offsite in a warehouse facility in southern Virginia.
  • Continue installation of elevated underfloor mechanical and electrical and telecom utilities.
  • Complete installation of brick on building elevation mock up.
  • Continue installation of underground utilities on north and south ends of new building.
  • Start layout of partitions on floor 4.
  • Continue spray on fireproofing floors 1 and 2.

Utility Infrastructure Project

Week of October 21:

  • Continue to excavate for new underground electrical and telecom for future Wilkins Plaza event power, light poles, and Wi-Fi.
  • Continue work on new concrete serpentine wall in Phase 3 (Wilkins Plaza east extension) area. 
  • Pipe delivery continues for Phase 4 (Southside east to Central Heating and Cooling Plant) areas.
  • Continue trenching and pipe installation in Phase 4 areas.
  • Closure of Rivanna River Road as pipe is delivered and installed in Phase 4 areas. This closure will continue through early November. This work has been delayed a due to unforeseen underground conditions and pipe manufacturing problems. 

  Week of October 28:

  • Continue to excavate for new underground electrical and telecom for future Wilkins Plaza event power, light poles, and Wi-Fi.
  • Continue work on new concrete serpentine wall in Phase 3 (Wilkins Plaza east extension) area. 
  • Pipe delivery continues for Phase 4 (Southside east to Central Heating and Cooling Plant) areas.
  • Continue trenching and pipe installation in Phase 4 areas.
  • Closure of Rivanna River Road as pipe is delivered and installed in Phase 4 areas. This closure will continue through early November. This work has been delayed due to unforeseen underground conditions and pipe manufacturing problems.