Core Campus Project: Two-Week Planner, June 17–28

Robinson Hall Replacement

Week of June 17:

  • Continue excavation for foundations and underground mechanical work.
  • Continue to pour concrete at new building foundations.
  • Continue waterproofing of new foundation walls.
  • Continue to pour slab on grade for lowest level of new building.
  • Complete landscape and hardscape restoration of site around Harris Theatre.
  • Procurement of materials for full scale building envelop mock up.
  • Plan for delivery of crane to support steel erection of new building.

Week of June 24:

  • Continue excavation for foundations and underground mechanical work.
  • Continue to pour concrete at new building foundations.
  • Continue waterproofing of new foundation walls.
  • Continue to pour slab on grade for lowest level of new building.
  • Complete landscape and hardscape restoration of site around Harris Theatre.
  • Procurement of materials for full scale building envelop mock up.
  • Plan for delivery of crane to support steel erection of new building.
  • Begin underground utility installation on northeast corner of new building site.
  • Pour foundation for exterior building skin mock up at the southeast corner of the site.

Utility Infrastructure Project

Week of June 17:

  • Continue site restoration in Phase 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza), and 2B (West Building) areas.
  • Continue hardscape and landscape restoration in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2 (Musi/Theatre, West Building) areas.
  • Continue to re-install site lighting in Phase 1 and 2 areas.
  • Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from clock to Southside Plaza).
  • Continue trenching in Phase 4 areas (Southside east to Central Heating and Cooling Plant).
  • Continue trenching in Phase 6 areas (near Commonwealth and Dominion Halls).

Week of June 24:

  • Continue site restoration in Phase 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza), and 2B (West Building) areas.
  • Continue hardscape and landscape restoration in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2 (Musi/Theatre, West Building) areas.
  • Continue to re-install site lighting in Phase 1 and 2 areas.
  • Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from clock to Southside Plaza).
  • Continue trenching in Phase 4 areas (Southside east to Central Heating and Cooling Plant).
  • Continue trenching in Phase 6 areas (near Commonwealth and Dominion Halls).