Core Campus Project: Two-Week Planner, July 1–12

Robinson Hall Replacement

Week of July 1:

  • Complete new concrete building foundations.
  • Continue waterproofing of new foundation walls.
  • Continue installation of underground mechanical and plumbing work.
  • Continue to pour slab on grade for lowest level of new building.
  • Complete punch list items for landscape and hardscape restoration of site around Harris Theatre.
  • Procurement of materials for full scale building envelop mock up.
  • Finalize plan for delivery of crane to support steel erection of new building.
  • Continue underground utility installation on northeast corner of new building site—this work will impact pedestrian walkways during overnight work.

Week of July 8:

  • Complete waterproofing of new foundation walls.
  • Continue installation of underground mechanical and plumbing work.
  • Continue to pour slab on grade for lowest level of new building.
  • Complete punch list items for landscape and hardscape restoration of site around Harris Theatre.
  • Procurement of materials for full scale building envelop mock up.
  • Beginning Friday, July 12, through Monday, July 15, the crane will be delivered to site in preparation for steel erection.
  • Finalize underground utility installation on northeast corner of new building site—this work will impact pedestrian walkways during overnight work.

Utility Infrastructure Project

Week of July 1:

  • Continue site restoration in Phase 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza), and 2B (West Building) areas.
  • Continue hardscape and landscape restoration in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2 (Music/Theatre, West Building) areas.
  • Finalize re-install of site lighting in Phase 1 and 2 areas.
  • Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension from clock to Southside Plaza).
  • Continue trenching in Phase 4 areas (Southside east to Central Heating and Cooling Plant).
  • Continue trenching in Phase 6 areas (near Commonwealth and Dominion Halls).

Week of July 8:

  • Continue site restoration in Phase 1A (Aquia Creek Lane), 1B Johnson Center South Plaza), and 2B (West Building) areas.
  • Continue hardscape and landscape restoration in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2 (Music/Theatre, West Building) areas.
  • Finalize re-install of site lighting in Phase 1 and 2 areas.
  • Continue trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension from Clock to Southside Plaza).
  • Pipe delivery to begin for phase 4 (Southside east to Central Heating and Cooling Plant) and 6 (near Commonwealth and Dominion halls) areas.