Core Campus Project: Two-Week Planner, February 25 to March 8

Robinson Hall Replacement

Week of February 25:

  • Begin sheeting, shoring and excavation activities.
  • Continue installation of high temperature hot water and chilled water utilities to Harris Theatre.
  • Continue interior improvements in Harris Theatre service/utility area.
  • Continue relocation of utilities on the site of Robinson A.
  • Continue to install exterior enclosure on Robinson B after Robinson A is removed.

Week of March 4:

  • Continue sheeting, shoring and excavation activities.
  • Continue installation of high temperature hot water and chilled water utilities to Harris Theatre.
  • Continue interior improvements in Harris Theatre service/utility area.
  • Continue relocation of utilities on the site of Robinson A.
  • Continue to install exterior enclosure on Robinson B after Robinson A is removed.

Utility Infrastructure Product

Week of February 25:

  • Pipe installation and backfill to continue in Phase 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza) and 2B (West Building) areas.
  • Testing in phase 1A and 1B areas.
  • Continue backfill and site restoration in Phase 2A areas.
  • Continue hardscape and landscape restoration in phase 1A and 1B areas.
  • Continue to re-install site lighting in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2A (Music Theater) areas.
  • Begin trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from Clock to Southside Plaza).
  • Complete second outage for permanent tie in to Aquia Building. Planned outage for Aquia Building, Fenwick Towers, MIX and SUB I.

Week of March 4:

  • Pipe installation and backfill to continue in Phase 1A (Aquia Creek Lane), 1B (Johnson Center South Plaza) and 2B (West Building) areas.
  • Testing in phase 1A and 1B areas.
  • Continue backfill and site restoration in Phase 2A (Music Theater) areas.
  • Continue hardscape and landscape restoration in Phase 1A and 1B areas.
  • Continue to re-install site lighting in Phase 1 (Aquia Creek Lane, Johnson Center South Plaza, EagleBank Arena) and 2A areas.
  • Begin trenching and pipe installation in Phase 3 areas (Wilkins Plaza extension - from Clock to Southside Plaza).