Core Campus Project: Two-Week Planner July 23- August 5

Core Campus Project 2-week Look Ahead 7/23/2018 - 8/5/2018

New Academic Building:
Week of July 23rd –
  • Construction Fencing will be arriving on site and will begin installation – it will take approximately 2 weeks to install all site fencing.
  • Preparing Submittals and Shop Drawings for Long Lead Equipment Orders
Week of July 30th –
  • Construction fence installation continues – signs for pedestrian re-routes are installed
  • Fire Wall Patching in Robinson B
  • Hazardous Materials Abatement begins in Robinson A
Utility Infrastructure Project:
Week of July 23rd –
  • Construction fencing installation continues in near Thompson Hall and down Aquia Lane, south of Johnson Center and Patriot Circle to Eagle Bank Arena
  • Construction fencing at laydown area and job site office trailers delivered to site previously occupied by student apartments.
  • Shop Drawings approved and piping ordered for phases 1A, B and C
Week of July 30th - 
  • Installation of erosion and sediment control measures including silt fencing and etc.
  • Temporary pathways installed in areas where sidewalks disrupted
  • Vegetation, signs, light fixtures and etc. in construction areas removed.
  • Signs installed for re-routing pedestrian routes on campus