Improve Utility Distribution Infrastructure Fairfax

East Fountain

4400 University Drive, Fairfax, VA 22030

Details

Project Number: 18208-000

Project Type: Renovation/Improvement

Campus: Fairfax

Biennium: 2016 -2018

Authorization: Board of Visitors

Project Phase: Construction

Budget

Total Project Budget: 51,371,000

Schedule

Design Start: April 2016

Design Complete: August 2018

Construction Start: August 2018

Construction Completion: December 2021

Project Team

University Project Manager: Cathy Wolfe-Pinskey

Advising A/E: Gordon Engineering Firm – Perkins+Will

General Contractor:The Whiting-Turner Contracting Company