Hylton Performing Arts HVAC Renovations

Hylton

10960 George Mason Cir 

Manassas, VA 20110

Details:

Project Number: A8247-024

Project Type: Renovation/Improvement

Campus: Science and Technology

Authorization: Board of Visitors

Project Phase: Construction

Key Building Occupants: College of Visual and Performing Arts

Budget

Total Project Budget: 3,820,598

Schedule:

Construction Start: September 2018

Construction Completion:  June 2021

Status

Renovate the Hylton PAC HVAC system to provide more consistent humidity control and comfort for the patrons.

Project Team:

University Project Manager: Mike Herman

Architect/Engineer: Quinn Evans Architects

General Contractor: Alta Vista Consultants, LLC

Unit Space Liaison: CVPA – Rick Davis