Horizon Hall

Horizon Hall

Construct/Renovate – Robinson Hall and Harris Theater

4473 Aquia Creek Lane, Fairfax, VA 22030

Details

Project Number: 18207-000

Project Type: New Construction

Campus: Fairfax Campus

Authorization: State Legislature

Project Phase: Construction 

Interiors Phase: Complete

Budget

Construction Budget: 108,316,000

Schedule

Design Start: April 2016

Design Complete: November 2018

Construction Start: September 2018

Construction Completion: December 2021

Project Team

University Project Manager: Cathy Wolfe-Pinskey

Planner: Laura Manno

Advising A/E:  Perkins+Will