Project Timeline

CORE CAMPUS PROJECT TIMELINE
New Academic Building (Horizon Hall) and Utility Infrastructure Upgrade

 

SPRING 2021

New Academic Building (Horizon Hall)

  • New academic building open for start of spring 2021 classes
  • Robinson B is vacated and decommissioned; hazardous materials removed and demolished
  • Harris Theatre closes for renovations

Utility Infrastructure Upgrade

  • Complete Wilkins Plaza upgrades: new sidewalk, pavers with concrete base and statue base in Phase 7 area
  • Complete sod and vegetation installation in Phase 7 area
  • Demolition and removal of existing sidewalk, steps, pavers in Phase 8 area
  • Complete trenching, utility installation, and backfill of Phase 8 area
  • Install new water feature fountain as part of Phase 8 area
  • Complete Wilkins Plaza upgrades: new sidewalk, pavers with concrete base and statue base in Phase 8 area

Planned Outages

  • SUB I chilled water outage (date TBD)

SUMMER 2021

New Academic Building (Horizon Hall)

  • Site work begins in area of demolished Robinson B building
  • Harris Theatre addition and renovations continue

Utility Infrastructure Upgrade

  • Complete sod and vegetation installation in Phase 8 area
  • Re-install George Mason statue
  • Complete installation of Enslaved Persons of George Mason Memorial on Wilkins Plaza

Planned Outages

None

FALL 2021

New Academic Building (Horizon Hall) 

  • Site work is complete by end of fall 2021
  • Harris Theatre renovations are complete by end of fall 2021

Utility Infrastructure Upgrade

  • Complete punch list items for utilities distribution infrastructure project

Planned Outages

None